- Additional man hours were allocated to meet tight deadlines for initial steelwork.
- To address revisions to models and completed drawings, Advance Steel was utilised for renumbering of models and to allow for revisions between stages.
- To ensure installed steel did not need to be modified due to changes during fabrication, alternate marking plans were produced.
- iConstruct software enabled creation of an intelligent colour coded site model to track steel on site.
- Modelers were integrated within the client’s office to work alongside the design team and provide optimal solutions in managing design changes and improving time frames.

Fast Facts

October
Project Commenced

+
Shop Drawings

+
Man Hours